Scheduling Time Line
The Project tasks :
- Record and data analysis related with the enviroment and database requirements (RDA)
- Data base INPUT/OUTPUT specification (DB&IOS);
- Mathematical modeling and algorithm development of optimal splice connections and optimal splice location problems ( MM-OSC&OSL);
- Database and Interface implementation (DB&II);
- Implementation of the test version of the solvers (ITVS);
- Installation of the test version at Porto Technical Centre ( ITV-PTC);
- Computational experiments with real data and refinement of the test version ( CE&RTV);
- Implementation of the final version (IFV);
- Installation of the different modules and test at Porto Techinal Centre (I&T-PTC);
Months |
1 |
2
|
3
|
4
|
5
|
6
|
7
|
8
|
9
|
10
|
11
|
12 |
13
|
RDA
|
X |
X |
X | ||||||||||
DB&IOS
|
|
X |
X |
X
|
|||||||||
MM-OSC&OSL
|
X |
X |
X |
X
|
X
|
||||||||
DB&II
|
|
X |
|
X |
X | X |
X
|
X
|
|||||
ITVS
|
X | X |
X |
X |
X |
X
|
Months |
14
|
15
|
16
|
17
|
18
|
19
|
20
|
21
|
22
|
23
|
24 | |
DB&II
|
X |
|
||||||||||
ITVS
|
X |
|
|
|
||||||||
ITV-PTC
|
X |
|
|
|||||||||
ICE&RTV
|
X |
X
|
X |
|
|
|
||||||
IFV
|
X |
X |
X |
X |
|
|
||||||
I&T-PTC
|
X |
X |
RDA = Record
and data analysis
DB&IOS = Data base and INPUT/OUTPUT specification
MM-OSC&OSL = Mathematical modeling and algorithm development of optimal splice connections and optimal location problems
DB&II = Database and Interface implementation
ITVS = Implementation of the test version of solvers
ITV-PTC = Installation of the test version of solvers
CE&RTV = Computational experiments with real data and refinement of the test version
IFV = Implementation of the final version
I&T-PTC = Installation of the different modules and test at Porto Techinal Centre
DB&IOS = Data base and INPUT/OUTPUT specification
MM-OSC&OSL = Mathematical modeling and algorithm development of optimal splice connections and optimal location problems
DB&II = Database and Interface implementation
ITVS = Implementation of the test version of solvers
ITV-PTC = Installation of the test version of solvers
CE&RTV = Computational experiments with real data and refinement of the test version
IFV = Implementation of the final version
I&T-PTC = Installation of the different modules and test at Porto Techinal Centre