Scheduling Time Line


    The Project tasks :

  •  Record and data analysis related with the enviroment and database requirements (RDA)
          •  Data base INPUT/OUTPUT specification (DB&IOS);
          •  Mathematical modeling and algorithm development of optimal splice connections and optimal splice location problems ( MM-OSC&OSL);
          • Database and Interface implementation (DB&II);
          • Implementation of the test version of the solvers (ITVS);
          • Installation of the test version at Porto Technical Centre ( ITV-PTC);
          • Computational experiments with real data and refinement of the test version ( CE&RTV);
          • Implementation of the final version (IFV);
          • Installation of the different modules and test at Porto Techinal Centre (I&T-PTC);
   

Months
1
2
3
4
5
6
7
8
9
10
11
12
13
RDA

X

X
X
DB&IOS

X

X
X
MM-OSC&OSL

X

X

X
X
X
DB&II

X

X
X X
X
X
ITVS
X
X

X

X

X
X

Months
14
15
16
17
18
19
20
21
22
23
24
DB&II

X
ITVS

X
ITV-PTC
X

ICE&RTV

X
X
X
IFV

X

X

X

X
I&T-PTC

X

X
RDA = Record and data analysis
DB&IOS = Data base and INPUT/OUTPUT specification
MM-OSC&OSL = Mathematical modeling and algorithm development of optimal splice connections and optimal location problems
DB&II = Database and Interface implementation
ITVS = Implementation of the test version of solvers
ITV-PTC = Installation of the test version of solvers
CE&RTV = Computational experiments with real data and refinement of the test version
IFV = Implementation of the final version
I&T-PTC =  Installation of the different modules and test at Porto Techinal Centre